The first production well targeting oil reserves within the framework of free natural gas (FNG) production at the “Azeri-Chirag-Gunashli” (ACG) fields block has been commissioned.
This is reported by elchi, citing BP’s report on the results of the first 9 months of this year regarding its activities in Azerbaijan.
According to the information, with the commencement of FNG production operations at ACG in the first half of 2026, the field entered the phase of its first commercial gas production operations.
It is reported that the first FNG production operations at ACG began in the first production well targeting two priority FNG reservoirs located beneath the oil reservoirs, drilled in 2025 and currently in production – the shallower Upper Kirmaki Sand and the deeper Lower Kirmaki Sand reservoir sets. The well confirmed the presence of gas reserves in the Upper Kirmaki Sand reservoir set and discovered the presence of high-pressure gas reserves in the Lower Kirmaki Sand reservoir set.
According to the information, FNG production operations are currently ongoing in the Lower Kirmaki Sand reservoir set and include not only initial production but also testing operations in the well and reservoir set.
The gas and condensate produced from the well are sent to the Sangachal terminal using the existing ACG infrastructure through the integration of oil and gas processing systems, which creates an opportunity for efficient use of existing offshore facilities.
In addition to the first FNG production well, a production well targeting the oil reserves of FNG reservoirs has been drilled from the “Deepwater Gunashli” platform and commissioned by the end of the third quarter of 2026 as planned. Additional appraisal data is also expected from this well, which will help assess future development opportunities in the FNG reservoirs.
It should be noted that stable production from ACG continued safely and reliably during the third quarter of 2026. Total production from ACG for the first three quarters – combined from the “Chirag” (18,800), “Central Azeri” (84,600), “West Azeri” (72,000), “East Azeri” (45,700), “Deepwater Gunashli” (46,700), “West Chirag” (25,300), and ACE (26,900) platforms – averaged 320,000 barrels per day, or approximately 87 million barrels in total, which is 12 million tons.
At the end of September, a total of 154 oil production wells, 50 water injector wells, and 11 gas injector wells were in operation at ACG.
It should also be added that during the first three quarters of the year, 12 oil production wells, 3 water injectors, and 2 gas injectors were drilled and completed at ACG.
One of these wells – the D18Z oil production well drilled from the “East Azeri” platform, is a significant achievement for the ACG project, being the well with the longest reservoir contact drilled to date in the ACG field. The well has an open hole section of over 2000 meters, with more than 1500 meters of it passing through the sand section within the target productive reservoir. This achievement further emphasizes the role of advanced seismic imaging, drilling, and completion technologies in unlocking additional value from the ACG field.